Twintec carries out the final regulating layer preparation using laser controlled equipment which remains on site for the duration of the works. This delivers very accurate tolerances (+/- 5mm) and provides the platform for the superflat floor slab casting process.
Joints are always the greatest cause of problems on superflat floors in modern warehouses. In advance of concrete works, metal armoured joints with heavy duty load transfer systems are installed at the perimeter of every day’s work. The chosen joints are durable, low in maintenance cost and located (as far as possible) in low traffic zones.
The integration of steel fibres into the concrete is carried out on site using trained operators and the latest third-generation fibre integration machines. Superplasticiser is added to the concrete, and then the machines separate and orientate the fibres and introduce them into the plasticized concrete, guaranteeing uniform distribution.
Twintec use flood pour techniques with large areas of concrete placed and levelled in one day using a laserscreed machine. Areas up to 4000m2 per day are achievable.
Created from a course carborundum-based blend of aggregates, Twintec applies the dry shake topping shortly after the concrete has been placed and initially levelled. This not only suppresses the fibres in the matrix of the slab, but also adds a significant layer of additional material with outstanding abrasion resistance across the superflat floor.
While the concrete is still plastic, Twintec measures the surface in relation to the specified tolerance and reworks the surface until the specialist tolerance is achieved. Experienced operators with state-of-the-art equipment flatten and densify the surface. Using this system, Twintec can create flatness tolerances of FM1, FM2 Special, CAT1 and DM2.